What is a rigging plan?

Prepare for the Operating Engineer Exam with interactive quizzes, flashcards, and multiple-choice questions complete with hints and explanations. Ensure success on your first try!

A rigging plan is a detailed outline that specifies how loads will be lifted and moved safely. This plan typically includes crucial information such as load weights, lifting equipment (like cranes or hoists), the type of rigging gear (such as slings and shackles), safety measures, and the specific movements and paths that loads will take during the lift or transfer. The purpose of having a robust rigging plan is to ensure the safety of personnel and equipment on the job site, minimizing the risk of accidents or load failure. It is essential for all involved in the operation to be clear on the plan to execute the lifting process safely and efficiently.

The nature of other options, such as strategies for erecting scaffolding, records of equipment used on-site, or methods for training workers, strays from the primary focus of rigging. These concepts, while important in the context of construction and operational safety, do not encapsulate the specifics and objectives of a rigging plan.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy